Changeover to Air Conditioning in the Works
| |
 |
| |
Claude Rioual
descends into a manhole while Dan Benvenuto secures safety
equipment. |
The annual campus-wide operation that results in the conversion from
winter heat to summer air conditioning for most Trinity buildings has
begun. Assistant Plant Engineer Jim Egan and his two-man crew, Energy
Plant Specialist Claude Rioual and HVAC Technician Dan Benvenuto,
started the approximately two-week process on Thursday, April 29, by
shutting down the boilers that keep the College’s hot water system at
210 degrees during the winter. That water, which runs through
insulated, underground pipes, must be allowed to cool naturally to
roughly 80 degrees before it can be fed into the chiller system. That
process then cools the water to 40 degrees, which is used to produce
air conditioning.
After more than nine years at Trinity, Egan is well aware that most
people on campus have no idea of the complexity of the changeover
process. The initial challenge is to decide on a date to shut down the
boilers. “While faculty and staff are, for the most part, only in
their offices during the day, our students live here 24 hours a day,”
says Egan. “It can still get pretty cold at night, even when we’re
having warm afternoons. We try to wait until we think the cold weather
is really behind us, but it’s always a gamble.” The decision to start
the conversion is made based on current forecasts combined with
average temperatures over the last five years.
Once the boilers are turned off, meaning that the water in the
two-pipe system is no longer being heated, Egan and his crew begin the
arduous process of redirecting the flow from the boilers into the
chillers. The College has three main boilers in the Central Energy
Plant; two are in use while one is always on standby. They are fed
through pipes that run virtually under the entire campus. The water is
manually redirected through an intricate series of valves and
shut-offs, which are accessed through manholes around campus or are
located in the basements of buildings.
In addition to redirecting the water flow via the valve system, each
building’s air-handler and coil system must be thoroughly tested
before the air conditioning system can be activated. The crew does
this while they are waiting for the water to cool down. Any necessary
repairs are made before the air conditioning is turned on, thereby
avoiding costly problems once the system is brought on line.
“This isn’t like your home heating and cooling system,” explains Egan.
“We do this twice a year—in the spring and in the fall. Once we shut
down the boilers, they’re down; same with the chillers. That’s why we
try to make sure that everything is operating properly before we
activate the system each time. We try to make this as painless as
possible.”
back
to top
Return to eQuad table of
contents
|